Fixing Streets - Measure S

PCI Status, July, 2020

Pavement Condition Index (PCI) PCI of 69Pavement Condition Index (PCI) Status, as of July, 2020

Measure P 2015 - 2019

Measure P Fourth Year Report

Fourth Year Report | PDF Version
Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Fixing Streets Measure S Sign


Week beginning
November 23, 2020:

Please note: Schedule is subject to change. MASTER PROJECT SCHEDULE
  1. MEASURE S Citywide Curb Ramps Phase 3 - Downtown
  2. Lower POM (Corp Ewing Road) - Lower PoM Construction - Parking is open - Two dilapidated structures next to the lot being removed.
  3. Pine and Hawthorne streets storm drain and bulb outs - SEE UPDATED SCHEDULE | NOTICE (NCIP)
  4. Fire Suppression on Wharf 2 - Installation of new fire sprinkler system at the end of Wharf II - work is ongoing
  1. MEASURE S Citywide Road Rehab. Ph.1 - Mar Vista Dr. (From Mar Vista to Monte Vista), Ramona Ave. (Montecito to Fremont), Munras Ave. (Munras to Fremont).
  2. MEASURE S Citywide Sidewalk Phase 5 - Downtown and Oldtown areas
  3. MEASURE S Franklin Street Storm Drain Improvements

Caltrans to perform work on two major Monterey Peninsula arteries - Highway 68 and Highway 156 traffic will impacted over two days each next week. For more information on this project and for traffic updates on other Caltrans projects in Monterey County, call the District 5 Public Affairs Office at (805) 549-3318 or visit the website at dot.ca.gov/caltrans-near-me/district-5.

Measure S Tax Quick Facts

As of April 1, 2019 - Measure P is now Measure S

Thank you for saying yes to Measure S