Fixing Streets - Measure P

Measure P Street Resurfacing Status Map Measure PProject Status Map, Aug. 2017

Fixing Streets Measure P Sign

Measure P Second Year Report

Second Year Report | PDF Version

First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
November 20:

Please note: The schedule is subject to change.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • MEASURE P: ADA Ramp and Street Reconstruction Phase 5 - Work expected into early March in Old Town, specifically one block of Larkin Street and two blocks of Watson Street -SEE MAP
  • Pacific Street Sidewalk Reconstruction Phase 2 - 1100 block - See Project Info - Work expected to last into early Dec. (NIP)
  • MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 5 - Currently markings, striping, and additional cleanup to complete.
  • Wharf II Pile Replacement & Repair - Critical repairs continue. Completion expected some time in December. (CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Installation of the new 36” water pipeline continues on Fitch Avenue in the Presidio of Monterey on Friday, November 17, through Wed., Nov. 22 to complete the crossing of Kit Carson Road. Work hours are 7 a.m. to 5 p.m. Traffic controls and parking limitations will be posted. Work will suspend Thursday, November 23 for the Thanksgiving holiday and resume on Monday November 27. Nighttime construction work in downtown Monterey, which had been delayed due to the discovery of an unmarked, underground utility line, is expected to resume on Webster Street and Munras Avenue on the evening of Sunday, November 26, between the hours of 7 p.m. to 6 a.m. Traffic controls will be posted. Hydrant tie-ins will occur near the Fairgrounds in Monterey. Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays, July 2017 to Fall 2018 - Work to close Hoffman between Cannery Row and Wave Street, tentatively scheduled for Nov.28, Dec. 5, and Dec. 11, weather permitting.

construction signs

Upcoming

  1. El Estero Streetscape, Phase 3 - adding parallel parking spaces - details coming soon. This work should be completed within 30 days.
  2. Street lights on Franklin and Alvarado - Details coming soon
  3. Sidewalk work at bus stop on David Ave. - Details coming soon
  4. North Fremont Bike and Pedestrian Access and Safety Improvement Project - bidding takes place early spring 2018 - learn more about this project: monterey.org/NFremontBikePed and sign up for email updates.

Ongoing

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts