Project Title
Larkin Bridge Seismic Retrofit
TYPE OF WORK:
Seismic Retrofit
FUNDING SOURCE:
Partially funded with a grant from the Federal Highway Bridge Replacement Rehabilitation Program
CONTACT:
Construction Management
831.646.3997
(suggest@ci.monterey.ca.us)
DESCRIPTION and PURPOSE OF PROPOSED CONSTRUCTION
The Larkin Street Bridge Seismic Retrofit project consists of seismically retrofitting and repairing the existing bridge and the street improvements associated with these bridge improvements. The work includes seismic retrofit and repair of the bridge deck, bents, foundation and precast concrete arch culvert, construction of curb ramps and installation of necessary traffic signing and striping. This project is partially funded with a grant from the Federal Highway Bridge Replacement Rehabilitation program.
 

SCHEDULED TIME FRAME
NOTE: The construction dates are approximate and may vary due to weather or unforeseen conditions.

BEGIN: Aug. 29, 2005
ESTIMATED COMPLETION DATE : July, 2008

UPDATES/REVISIONS:

News Release

Project Photos - most recent first

TRAFFIC IMPACT
Some traffic delays can be expected during construction.

 
Concrete Fill between Arches and Bottom of Roadway  12/21/07

 
Sliding Arches in Place

 
Lifting 29,000 lb. Precast Arch to be placed under
Existing Bridge Structure.  09/25/07

 

Pumping 105 Cubic Yards of Concrete 8/31/06

 

Loading Concrete

 

Excavation Operations under and along the side of the Bridge  7/12/06

BEFORE

 


Return to Construction/Traffic Updates Main Page