Project Title |
Street Reconstruction at David Avenue
and Wave Street
|
TYPE OF WORK:
Sewer Repair and Street Reconstruction |
FUNDING SOURCE:
Capitol
Improvement Program - General Funds |
CONTACT:
Construction Management
831.646.3997
(suggest@ci.monterey.ca.us) |
|
DESCRIPTION and PURPOSE OF PROPOSED CONSTRUCTION |
| Sanitary sewer
sport repair and reconstruction, and pavement rehabilitation at David
Ave. between Divisadero St. and Lighthouse Ave.; and Wave St. between
David Ave. and Hoffman Ave. |
SCHEDULED TIME FRAME
NOTE: The construction dates are
approximate and may vary due to weather or unforeseen conditions. |
| BEGIN: |
Wave St.:
Mar. 5, 2008
David Ave.: Mar. 12, 2008 |
| ESTIMATED
COMPLETION DATE : |
Wave St.:
Mar. 21, 2008
David Ave.: May 23, 2008 |
|
UPDATES/REVISIONS:
News Release

David and Wave Construction Schedule 
5/16: 99% completion. A second coat of paint
will be applied the first week of June. |
|
TRAFFIC IMPACT |
|
Traffic delays and construction noise are expected during construction. |