PROJECTS FULLY FUNDED WITH BASE ALLOCATION

  1. CONA Preschool Play Area Decking
    Plastic wood 2" x 6" decking entire area of pre-school play area flush with the present concrete step.
     
  2. Install Rubber Surface in Tot Lot @ Laguna Grande Court Park
    Existing tot lot surface is wood chips. Residents have asked us to install rubber to reduce slivers and animal feces.
     
  3. Hoffman/Grace Retaining Wall
    The slope of the corner property is eroding onto the pavement at the stop sign. A small wall will hold the slope in place.
     
  4. ADA Curb Ramps Phase I (New Monterey)
    This will begin a program to install curb ramps at the most used intersections in the New Monterey neighborhood.
     
  5. Cannery Row Park Plaza Lighting
    Install lighting in the area between Foam Street and the Recreation Trail.
     
  6. ADA Curb Ramps (Del Monte Beach)
    This will install curb ramps in the Del Monte Beach neighborhood.
     
  7. Ruth Vreeland Monument – San Carlos Beach
    Install a monument plaque in the "seat rock" at San Carlos Beach Park for former Councilwoman Ruth Vreeland.
     
  8. Josselyn Canyon Mirrors at Monterey Woods
    Install convex mirror opposite the Monterey Woods entrance/exit to help see motorists coming down Josselyn Canyon.
     
  9. ADA Curb Ramps (Oak Grove)
    This will install curb ramps in the Oak Grove neighborhood.
     
  10. CONA Community Center Window Openers
    Provide motor operated window openers for the high windows in the Community /Center for better ventilation.
     
  11. Vet’s Park Expansion – Design
    The quarry area of Veteran’s Park is unused and is unattractive. This project would look at the potential for expanding the campground into this area.
     
  12. Mar Vista Bulbouts at Toda Vista
    This would add bulbouts at the crosswalks to lessen the distance traveled by the school children crossing the street.

Return to top


 PROJECTS FUNDED BY THE POT AND PARTIAL BASE ALLOCATIONS

  1. 2004 New Monterey Drainage
    Surface drainage improvements along the N/W side of the 1500 block of Hoffman Avenue and the West side of the 800 block of Lyndon Avenue.
     
  2. Via Mirada Traffic Calming
    A traffic study must be done first, but the proposed project is to construct bulbouts to slow traffic at 848 and 867 Via Mirada.
     
  3. Jefferson/Manzanita Median and Curb Extension
    This traffic calming project is to 1) construct an island on Jefferson Street between Manzanita Street and Clay Street and 2) construct bulb outs along Jefferson Street at the East intersection with Monroe Street.
     
  4. CONA Traffic Calming Phase III
    This is the construction phase of the approved traffic-calming plan. The plan would be to construct medians, bulb outs, crosswalks, landscaping and other traffic reducing measures until the budget is consumed.
     
  5. Aquajito Oaks Entryway Improvement Project
    This project will improve the landscaping entryway to the neighborhood along Littlefield Road. Improvements will include new trees and a rock grouping.
     
  6. Install Pedestrian Countdown Timers on Signal at Munras/Webster
    The old style "green hand/red hand" pedestrian crossing indicators will be replaced with the newer countdown timer indicators.
     
  7. Pacific Street Drainage and Shoulder Stabilization
    A new drainage swale and slope improvements will be constructed along the West Side of Pacific Street from Bartolomea Way to San Bernabe Way.
     
  8. Del Monte Grove Laguna Grande Traffic Calming Phase 4
    This is a continuation of construction of the approved traffic calming measures within this neighborhood.
     
  9. Monterey Sports Center, Remodel Women’s and Men’s Locker/Shower Rooms
    This project will replace lockers and tile in the men’s locker room and replace shower curtains, tile upgrades, soap and shampoo dispensers, and replace mirrors in the women’s locker room.
     
  10. Deer Flats Alley Resurfacing
    Fawn Lane between Elk Run and Caribou Court will be resurfaced and failed areas dug out and replaced.
     
  11. Sidewalk Fill In at 2151 & 2157 Trapani Circle
    This will complete the sidewalk fill in to the neighborhood park on Trapani Circle.
  1. Villa Del Monte Traffic Calming Study
    This will begin a traffic calming study to identify areas that specific traffic calming measures can be constructed.
     
  2. Via Gayuba Bulb Out Repair
    This bulb out has an inferior entrance structure that does not channel the storm water through the piping. This project will fix that.
     
  3. Del Monte Beach Traffic Signal Preemption for Ambulance Egress
    This would allow ambulances to deploy more quickly and safely by installing warning signs and devices for controlling the nearby traffic signal.
     
  4. Lower Jefferson Street Drainage
    This will add two "extended inlet" hoods to two catch basins, just above Pierce and Dutra, for extra inlet capacity.
     
  5. Greenwood Rise Improvements
    The asphalt on this cul-de-sac has failed because of undersurface water intrusion. The old asphalt will be removed and replaced with a base layer of drain rock to allow the water to pass through as it migrates down the hill.
     
  6. Casanova Oak Knoll Driveway Reconstruction
    The sidewalks in this neighborhood were constructed without proper roll curb driveways. Cars scrape their undersides when attempting to climb the curb and driveway pads. This project will reconstruct the curbs and ramps with proper roll curb driveways.
     
  7. Lower Presidio Walkway, Phase II
    This will reconstruct the crosswalk at Lighthouse / Private Bolio and connect the proposed walkway with phase I walkway. Pedestrians will be able to traverse the area without walking around the Lighthouse Curve roadway.
     
  8. Belden 400 Widening
    This will widen the 400 block of Belden Street to 36’ curb to curb. This will allow parking, sidewalks and two lanes of traffic.
     
  9. NIP Contingency Account FY 2005

Return to top


CUT-OFF PROJECTS *

  1. Madison Street 800 Block Street Improvements
    This will repair some pavement failures as the roadway heads down into the canyon just beyond Monroe Street.
     
  2. Airport Road Speed Enforcement Devices
    This will be a speed detection sign that will show the posted speed limit and the driver’s speed. One detection sign in each direction.
     
  3. Ferrante Park Irrigation Replacement
    This will replace the 20+-year-old irrigation system with new equipment and a more efficient layout pattern. Treated lake water is being explored.
     
  4. Fisherman’s Flats Miscellaneous Curb and Gutter Repairs
    This will remove and reconstruct various curb and gutter failures.
     
  5. Harrison Street Vets Park Pedestrian Access
    This will improve the steps and path from the top of Harrison Street into the back of Veteran’s park.
     
  6. Wall Construction along Herrmann at Via Paraiso
    Construct a small retaining wall around the North / West return to prevent parking and erosion.
     
  7. Hartnell Gulch Pedestrian Plan
    Begin the planning process to provide a pedestrian access from Pacific Street to Munras Avenue.
     
  8. San Carlos Beach Park Traffic Plan – Sign Program
    Signs to direct tourists and locals over to the businesses at Break Water Cove

* A budget appropriation adjustment will be brought before Council when funding is both identified and available

FY 04/05 NIP Contingency Account

$ 180,000

NEIGHBORHOOD IMPROVEMENT FUND TOTAL 

 $1,903,500

Return to top


Neighborhood Improvement Program
Return to Budget Main Page | Financial Policies
General Fund Revenues | Revenues by Program | Special Funds Revenues
General Fund Expenses | Operating Expenses by Program
Capital Improvements Program | Neighborhood Improvement Program
Staffing by Program | Demographics & Statistics | Budget News

hmpgbtm.gif (1747 bytes)

Revised 02/21/10 L. Huelga http://www.monterey.org/budget/2004_05/nipdescribe.html