Generally, neighborhood improvement projects are capital improvement projects that are of direct benefit to the various neighborhoods of the City. The projects included in this program are nominated by individual citizens or staff.  The NIP Committee is responsible for reviewing all of the projects that are submitted for funding from the NIP Fund, and then voting on which projects are to be recommended to Council for inclusion in the annual budget. For more info on the program, click here.

NEIGHBORHOOD IMPROVEMENT PROJECTS



Casanova Tree Program Phase 1
. This project will plant oak and Monterey Pine trees in the Casanova/Oak Knoll neighborhood under the supervision of the City Forester.  Budget: $5,000

CONA Center Storage. This project will construct an attached storage closet of approximately 10 square meters to the Casanova Oak Knoll park center building for storage capabilities to support the center’s programs. Budget: $10,000

Del Monte Grove/Laguna Grande Tree Planting Phase 1. This project will plant Monterey pine and oak trees in the Del Monte Grove/Laguna Grande neighborhood under the supervision of the City Forester. Budget: $3,930

Via Paraiso Park Storage Building. This project will add on to the existing storage building to accommodate maintenance equipment and will enhance storage capacity for the baseball league. Budget: $6,000

Taylor Street 600 Block Walkway Improvements, West side. This project will reconstruct the decomposed Granite walkway that has deteriorated and washed away during the "El Nino" storms. A more permanent asphalt walkway will be constructed. Budget: $8,000

Lottie Street 600 Block Drainage Improvements. This project will construct a drainline on the West side of the street. It will divert the runoff water into the drainline away from private property and eliminate puddles. Budget: $20,000

Oak Grove Trees, Phase II. This project will complete the tree-planting program in the Oak Grove neighborhood. Budget: $5,000

Return to top


Curb Ramps along Jefferson at Watson and Ord Streets. This project will construct four curb ramps at the intersection of Jefferson/Watson and two curb ramps at the intersection of Jefferson/Ord Streets. Budget: $6,000

Ferrante Park - Natural Noise Barrier. This project will plant more trees, vegetation and vines within the embankment that separates the park from the freeway. Budget: $11,785

Monte Vista Drainage – Category 1. This project will construct damage improvements for the high priority (category 1) property identified in the hydrology study "Hartnell Gulch: Watershed Analysis and Management Recommendation" for drainage problems in the Monte Vista area watershed. Budget: $200,000

Archer Park Improvements Phase II. This project will convert an asphalt parking area into a play area and add a full basketball court. This will complete the park improvements used by after-school children and neighbors. Budget: $65,000

Cooper Street Storm Drain Construction. This project will remove the existing asphalt pavement and construct a concrete "V" gutter along the entire length of Cooper Street. Also a subsurface drain field will be constructed to catch the subsurface water. Budget: $350,000

Standby Generator at Ryan Ranch Corporation Yard. This project will install a 200kw diesel powered generator to supply the City corp. yard with electrical power during emergencies or other power outages. This project will also wire other city facilities to allow the generator to "plug into" them for emergency electrical power. Budget: $150,000

San Carlos School Crosswalk Improvements. This project will shorten the crosswalk distance from curb to curb by constructing "bulb out" curbs and sidewalks, making the pedestrian crossing safer. Budget: $35,000

Return to top


Jacks Park Bleacher Area Modifications (Phase II). This project will demolish the existing snack shop and construct a closed bleacher unit behind home plate and construct a larger snack shop & announcers booth. The funding is one-half of the estimated cost. The Monterey PONY Baseball/Softball, Inc. organization is funding the other half. Budget: $65,000

Monterey Sports Center Expansion. This project will prepare construction plans and specifications for the building expansion. Budget: $150,000

Dennis the Menace Park – Renovate Play Equipment and Walkways. Dennis the Menace Park is well used and therefore requires constant maintenance and renovation. This project will renovate play equipment such as "the thing" and the suspension bridge and improve access. Budget: $75,000

Child Development Center at Presidio of Monterey. This project will repair the roof, remodel several rooms, landscape improvements, new carpet and paint, dumpster enclosure and upgrade play equipment. Budget: $100,000

Roberts Way – Entry Way Improvements. This project will realign the street to eliminate the blind driveway as you enter the neighborhood. This will require a new retaining wall, paving & striping. Budget: $42,000

Repair Sidewalks, Curbs and Realign Intersection at San Bernabe/Pacific. This project will construct curbs and sidewalk, curb ramps and a pedestrian crossing. The project will narrow down the intersection to allow safer pedestrian crossing and provide greater sight distance to drivers. Budget: $95,000

Return to top


Monterey Bay Park – Restrooms Phase II. This project will construct a restroom in the Phase II area of the park improvements just off Camino El Estero.  Budget: $100,000

Portola/Encina Alley Drainage. This project will construct a drain line from an existing catch basin to the curb face at Portola Avenue. The old "french drain" has silted up and no longer drains. Budget: $75,000

Replace Four Entrance Gates to Skyline Forest. This is the final construction phase of the project to remove the old entrance gates marking the entrances to Skyline Forest and construct newer less maintenance intensive entrance gates. Budget: $50,000

Colton Hall Grizzly Bears. This project will create and install bronze statues of California a Grizzly Bear and two cubs in front of Colton Hall. NIP is funding 1/3 of the project. Budget: $35,000

Sand Dunes Class 1 Bikeway & Habitat Restoration. This project will construct a Class 1 Bikeway from Casa Verde Avenue over the sand dunes to San Dunes Drive, eliminating three very hazardous crossings of Highway 1 on and off ramps. NIP is funding 5 ½ % of a $1.6 Million Project. Budget: $86,000

Veteran’s Park – A.D.A. Restroom Accessibility. This project will construct ADA access to restrooms in group area 2.
Budget: $5,000

Monterey Youth Center Renovation. This project provides additional funding for constructing improvements to the Youth Center. The work includes upgrading the restrooms, the teen room, the kitchen area and the large pre-school room. It includes developing a unisex restroom in the preschool area specifically for the young children. Budget: $75,000

Veteran’s Park – Renovation of Campsites, Roads & Entry. This campground is over 20 years old and needs repairs to the campsites and roadways. Also the entry needs repairs and upgrades. Budget: $45,000

Return to top


Lake El Estero Streetscape – Pearl Street Landscaping, Pavement & Parking Improvements. This project will provide landscaped median and parking bays and will complete the improvements that were done in front of the Youth Center in phase 1. Budget: $90,000

Franklin Street 800 Block - Driveway Replacements. This project will replace five short-length driveways with standard driveways. This will eliminate damage being done to the underside of cars from scraping the concrete.  Budget: $12,000

Handrail & Walkway from Parking Lot to Beach – Tide Avenue at Beach Way. This project will provide a wood walkway across the sand dunes to the high tide mark of the beach. Budget: $8,000

Curb Ramps on Jefferson at Larkin, Union & Van Buren Streets. This project will complete curb ramp installations at the three intersections.  Budget: $8,000

Lighted Crosswalk for the Sports Center - Franklin Street at Adams Street. This project will embed LED-flashing lights in the roadway on both sides of the crosswalk. A push button activation ballard will trigger the lights to visually alert motorists that pedestrians are in the crosswalk. Budget: $30,000

Irving/Wave Sidewalk & Curb Ramp Construction. This project will remove the large sweeping curb return on the South/West corner and construct a normal 10-meter curb radius with curb ramp. On the South/East corner an asphalt path around the large rock with a connection to the existing concrete sidewalk will be constructed.  Budget: $30,000

Curb & Gutter Reconstruction at # 615 Mar Vista. This project will remove approximately 15 meters of roll curb and gutter and roadway and replace them in a new vertical alignment so that the vehicles entering and exiting the driveway will not scrape. This is cut-off project # 1. Budget: $6,000

Whispering Pines Park – Phase II Improvements. This is the last phase of picnic improvements and will add landscaping, irrigation and a rock wall. This is cut-off project # 2. Budget: $35,000

Return to top



Return to:
Budget Main Page | Neighborhood Improvement Program


Budget Overview
Total Revenues - All | General Fund Revenues | Special Funds Revenues
Operating Expenditures - All | General Fund Operating Expenditures
Capital Improvements Program | Staffing by Program
General Fund Revenue & Expenditure Trends | Demographics & Statistics

City of Montery Home Page Button (1747 bytes)

Rev. 10/25/07 J. Splane http://www.monterey.org/budget/1999/nipdescribe.html