What's New

What's New lists City of Monterey or City of Monterey-sponsored events, office updates regarding city programs and services, news releases and city meetings. Other events around the community can be found at the Monterey County Convention and Visitor's Bureau, www.seemonterey.com.

I-SEARCH MontereyThe City Meetings Calendar lists meetings for City Council and Planning Commission. They can also be found on the Meetings tab at isearchmonterey.org. Dates are posted 3 days prior to the upcoming meeting.

For the very latest, Twitterfollow us on Twitter


News Search

Open bids posted on EbidBoard.com

Plans and Public Works

  • 28 June 2013
  • Author: Laurie Huelga
  • Number of views: 3686
  • 0 Comments
Open bids posted on EbidBoard.com

See open bids on EbidBoard.com

Print
Tags:

Name:
Email:
Subject:
Message:
x

Week beginning
May 22:

Please note: Weather may cause possible delays or changes to the schedule.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Citywide Street Resurfacing Phase 4 - See project schedule (Measure P)
  • Citywide Sidewalk Repair - See map and list of streets and dates | News Release- (Measure P, Phase 3)
  • Police Department Lobby ADA improvements
  • Citywide ADA Ramps and Street Reconstruction, Phase 3 - (Measure P) Sloat Avenue update: Planned delay to minimize impacts and coordinate with NPS summer schedule. Additional PG&E work added. (Through July)
  • Sewer Work - NO MAP this week - ("What a Relief")
    Work on Cannery Row between Drake and Dickman, 9 am to 9 pm, Wed., May 24
  • Citywide storm drain repairs, Phase 3 (Measure P) - Two areas left: Glenwood Circle and Abrego at Church Street
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Construction will resume on Jefferson Street between High Street and Monroe Street in Monterey. Pipeline installation in Seaside will continue onto Hilby Street between Fremont Boulevard and Wheeler Street.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Highway 68/Highway 1 Roundabout (monterey.org/hh68)
    Day and Night Work: Starting Monday 5/22 at 6 a.m., the connection from Holman Highway 68 to Southbound Highway 1 and the Pebble Beach Highway 1 Gate will be fully closed for 24 hours until Tuesday 5/23 at 6 a.m. The same full closure of the connection from Holman Highway 68 to Southbound Highway 1 and the Pebble Beach Highway 1 Gate will happen again on Tuesday night 5/23 from 8 p.m. to Wednesday morning 5/24 at 6 a.m. During the closures there will be no access from Holman Highway 68 to the Pebble Beach Highway 1 Gate or Southbound Highway 1 ramp (going towards Carmel). There will be access for a right turn ONLY exit out of Pebble Beach onto Southbound Highway 1. During the closure, drivers coming from Pacific Grove, Community Hospital, and the Aguajito Road neighborhood who are going towards southbound Highway 1 will need to follow the signed detour and head north on Highway 1 to make a U-turn at Munras Avenue. Large trucks and busses are advised to U-turn at Aguajito Road.
    During the closures:
    Emergency vehicles will have full access at all times.
    The CHP will be onsite to assist with traffic control.
    No closures are currently planned after Wednesday morning at 6 a.m. Additionally, the left turn from the Pebble Beach Highway 1 Gate towards Holman Highway 68 will be reopened after Wednesday at 6 a.m.
    Sign Up for Text Message Alerts - Text 68roundabout to 888777
    Sign-up to receive email notifications: www.tamcmonterey.org. TAMC will send a weekly “look-ahead” with info about the construction, road closures, detours, traffic conditions and travel options.
    HH68 Roundabout May Take Longer

construction signs

Ongoing


Upcoming

  1. ADA Ramp and Street Reconstruction Phase 4 on Littlefield, El Dorado and Pacific (Measure P) - July
  2. 300 Block of Belden Street Widening (NIP) - July
  3. Hawthorne Drainage Improvements - (CIP)
  4. Wharf II Pile Replacement & Repair - May 29 (CIP)
  5. Veteran's Park Bocce Ball Court - June (NIP)
  6. Alvarado Street Light Replacement - 26 street lights between Bonifacio and Del Monte - July (CIP)

CalTrans may be performing other work locally. Look up CalTrans construction.