Fixing Streets - Measure P

Fixing Streets Measure P Sign

Measure P First Year Report
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
May 29:

Please note: Weather may cause possible delays or changes to the schedule.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • MEASURE P STREETS: Citywide Street Resurfacing Phase 4 - See project schedule
  • MEASURE P SIDEWALKS: Citywide Sidewalk Repair Phase 3 - See map and list of streets and dates | News Release
  • MEASURE P ADA: Citywide ADA Ramps and Street Reconstruction, Phase 3 - Sloat Avenue update: Planned delay to minimize impacts and coordinate with NPS summer schedule. Additional PG&E work added. (into July)
  • Sewer Work - NO MAP this week - ("What a Relief")
    Work on Cannery Row between Drake and Dickman, 9 am to 9 pm, Thurs., June 1
  • Police Department Lobby ADA improvements
  • CalTrans Tree Trimming Work (Non-City Project)
    Daytime tree removal at multiple locations along Holman Highway 68. This work will require traffic control with flagging, so delays are anticipated.
    Work hours are 9 a.m. to 2 p.m.:
    - Tue. and Wed. 05/30 and 5/31 Eastbound Holman Highway 68 at CHOMP
    - Thu. 06/01/17 Eastbound Holman Highway 68 between CHOMP and Skyline Forest Drive
    - Fri. 06/02/17 westbound Highway 68 at Crocker Ave
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Construction will resume on Jefferson Street and then mid-week will move onto Monroe Street in Monterey. Pipeline installation in Seaside will continue onto Hilby. Pipeline installation in Seaside will continue Fremont Boulevard and Wheeler Street.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Highway 68/Highway 1 Roundabout (monterey.org/hh68)
    Next Tuesday night (May 30), crews will close the southbound Highway 1 off-ramp and the section of roadway between Holman Highway 68 and the southbound Highway 1 onramp from 8 p.m. to 6 a.m. in order to complete the removal of the traffic signal and reconfigure the intersection.
    During the closures:
    Drivers from Monterey wishing to go towards CHOMP/Pacific Grove will need to continue south on Highway 1 to make a U-turn at either Carpenter Street or Ocean Avenue and return to Holman Highway 68 via northbound Highway 1.
    - Drivers from CHOMP/Pacific Grove wishing to go south on Highway 1 towards Carmel will need to continue on northbound Highway 1 and make a U-turn at Munras Avenue or Aguajito Road and return to Carmel via southbound Highway 1. - Drivers from Pebble Beach will be able to make a right turn only out of the Highway 1 Gate towards Carmel.
    - The morning of Wednesday, May 31, the intersection will be controlled by yield signs. | MAP
    Sign Up for Text Message Alerts - Text 68roundabout to 888777
    Sign-up to receive email notifications: www.tamcmonterey.org. TAMC will send a weekly “look-ahead” with info about the construction, road closures, detours, traffic conditions and travel options.
    HH68 Roundabout May Take Longer

construction signs

Ongoing


Upcoming

  1. ADA Ramp and Street Reconstruction Phase 4 on Littlefield, El Dorado and Pacific (Measure P) - July
  2. 300 Block of Belden Street Widening (NIP) - July
  3. Hawthorne Drainage Improvements - (CIP)
  4. Wharf II Pile Replacement & Repair - Repairs 6/12, Pile driving 6/19 (CIP)
  5. Veteran's Park Bocce Ball Court - June (NIP)
  6. Alvarado Street Light Replacement - 26 street lights between Bonifacio and Del Monte - July (CIP)

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts