Fixing Streets - Measure P

Fixing Streets Measure P Sign

Measure P First Year Report
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
July 24:

Please note: Weather may cause possible delays or changes to the schedule.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Alvarado Street Light Replacement - 26 street lights between Bonifacio and Del Monte - Replacing fixtures with LED lights that are energy efficient and have a very long lifespan. Conforms to the Downtown Master Plan and has dimming capabilities. Starts Monday and expected to take four to six days. Little to no impacts to thoroughfare or noise level. (CIP)
  • Pearl Street Bridge Improvements -  replace walk path  (CIP)
  • 442 Casanova Avenue Sidewalk reconstruction, stump removal, curb and gutter ADA work all week (CIP)
  • 300 Block of Belden Street Widening Week two of 6 to 8 until completion - SEE CONTRACTOR SCHEDULE AND NOTICE (NIP)
  • MEASURE P STORM DRAINS: Citywide Storm Drain Repairs Phase 3 Storm drains on Walter Colton Drive near the school - next up - Soledad Drive at Soledad Place - potential road closure at times - dates still to be determined
  • MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 4 Phase 4 completed...phase 5 up next...details coming soon
  • MEASURE P SIDEWALKS: Citywide Sidewalk Repair Phase 3 - Small sections on Pacific, Tyler and Polk streets
  • MEASURE P ADA: Citywide ADA Ramps and Street Reconstruction, Phase 3 - Mostly completed; just line markings in some areas.
  • Wharf II Pile Replacement & Repair - Piles will be driven. Impacts to parking and traffic on the wharf. SCHEDULE in PDF (CIP)
  • Veteran's Park Bocce Ball Court (NIP)
  • Police Department Lobby UpgradesSee news release for details Lobby expected to re-open mid August.
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Pipeline construction will continue Madison Street in Monterey between Van Buren and Pacific Street. Crews will begin mobilization work in Pacific Grove near Sinex and Eardley Avenues. Appurtenance crews will move to Monroe Street in Monterey and continue work on Hilby Avenue. Paving will begin on North Fremont Street between Casa Verde and Hilby Avenues.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Highway 68/Highway 1 Roundabout (monterey.org/hh68)
    Next week crews will be focusing landscaping work, sidewalk work, as well as paving along southbound Highway 1 behind the concrete barriers under the Holman Highway 68 overpass. On Tuesday, crews will be pouring concrete for the last splitter island on the southbound highway 1 off-ramp. This work will require closing the free right turn lane of the off-ramp (going towards Pacific Grove) from 10 a.m. – 3 p.m. Drivers going towards Pacific Grove from the southbound Highway 1 off-ramp will need to proceed to the roundabout and make a right turn onto westbound Holman Highway 68.
    On Friday, crews will be working on a trench drain near the entrance to the Carmel Hills Professional Center, but no lane closure is currently planned for this work.
    Sign Up for Text Message Alerts - Text 68roundabout to 888777

    Sign-up to receive email notifications: www.tamcmonterey.org. TAMC will send a weekly “look-ahead” with info about the construction, road closures, detours, traffic conditions and travel options.
    HH68 Roundabout May Take Longer

construction signs

Ongoing


Upcoming

  1. Lower Presidio Historic Park Accessible Walkway up to the Sloat Monument (NIP)
  2. MEASURE P: ADA Ramp and Street Reconstruction Phase 4 on Littlefield, El Dorado and Pacific (Measure P) - early Sep
  3. MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 5

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts