Fixing Streets - Measure P

Phase 5 of Citywide Street Resurfacing Update

Update on September 1, 2017: Phase 4 slurry resurfacing work (this phase creates the most impact) is scheduled for October 6 through October 20 for all areas shown on the map.
Update on August 16, 2017: Citywide Street Resurfacing Phase 5 to begin in September in Neighborhoods
- some neighborhoods will soon receive a notice of work to begin from the contractor, Granite Construction.

THERE WILL BE SEVERAL PHASES TO THIS PROJECT:

  1. The first phase will entail crews adjusting iron (manholes, lids, etc.) in the street. - this is complete
  2. The second phase will be grinding and patch paving. (The Casanova Oak Knoll and Del Monte Grove/Laguna Grande neighborhoods are first on the list. Work in these neighborhoods is scheduled to begin at the end of next week.)
  3. The third phase will be marking removal, crack filling and sweeping.  
  4. The fourth phase will be resurfacing with a slurry seal.  
  5. The final phases will include readjusting iron, striping/markings (2 coats) and clean up.

Each of these phases will occur during the course of one working day. The notice you will receive from Granite Construction is for the second phase. You will be re-notified before the slurry work as this will have the greatest impact.

The notice from Granite Construction will be in more detail with date ranges included, as well as a phone number for any questions. Once you receive this notice, if you still have questions, you can also contact me and I can relay your questions for a response.

MAP OF STREETS

Weather and other circumstances can impact the schedule. Each Friday monterey.org/construction also gets updated with a list of major construction happening in Monterey. We thank you for your continued understanding and patience during these important infrastructure improvements.

Measure P Street Resurfacing Status Map Measure PProject Status Map, Aug. 2017

Fixing Streets Measure P Sign

Measure P Second Year Report

Second Year Report | PDF Version

First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
September 18:

Please note: The schedule is subject to change.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 5 - The slurry resurfacing portion of work (this phase creates the most impact) is scheduled for October 6 through October 20 for all areas shown on the map. Work continues to get the streets ready for the slurry. Next week this phase of work will finish in the Villa Del Monte and move to the Oak Grove neighborhood. MAP OF STREETS - SEE SPECIAL NOTICE FOR MORE DETAILS
  • Lower Presidio Historic Park Accessible Walkway up to the Sloat Monument (NIP) - estimated completion date is Nov. 6.
  • 300 Block of Belden Street Widening Belden Street section complete - associated work on Laine Street scheduled to be competed Fri., Sep. 22. (NIP)
  • MEASURE P: ADA Ramp and Street Reconstruction Phase 4 - Pacific Street Exit from Lighthouse Avenue closed - SEE NEWS RELEASE FOR DETAILS This work also closes Artillery Street. Drivers will need to use Bolio Road.
    - El Dorado Street between Major Sherman Road and Alta Mesa. Crews will be paving on Sat., Sep. 16 and the road will reopen Saturday evening. There will still be median work left to finish. - (Measure P)
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Crews will continue pipeline construction in New Monterey on Irving Street. Additional curb, gutter, and sidewalk and paving work will take place on Lily and Filmore. Paving work is also expected to take place on Monroe, Madison, Sinex and Withers streets.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays, July 2017 to Fall 2018
    Block of Hoffman at Cannery Row will be closed Tuesday, Sep. 19, between 7:30 a.m. and by 4:00 or 5:00 at the latest.
  • It's open! Holman Highway 68 Roundabout LIVECAM - Take a look at the intersection in real time

construction signs

Upcoming

  1. MEASURE P: ADA Ramp and Street Reconstruction Phase 5 - scheduled to begin in October.
  2. Wharf II Pile Replacement & Repair - Base job completed. Crews will return in late September to complete additional work.(CIP)
  3. MEASURE P STORM DRAINS: Citywide Storm Drain Repairs Phase 3 - Soledad Drive at Soledad Place - potential road closure at times - work scheduled to begin week of Sep. 25.

Ongoing

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts